password

Friday 3 June 2016

03-JUN-2016

🕸 Report date: 03-JUN-2016🕸
WAFTECH#3 CU SMT UPDATE

🎯Install label linear remover assembly
Progress: 65%
Current status: Design concept final stage 90%. Pending fabrication.
Due date: 17-June-2016 (improvement plan-can buy off without this first)

🎯 MC not detect if temperature thermal release out of spec
Progress:50%
Current status: Pending software
Due date: TBA
(Temperature controller setup complete, pending software)

🎯 Barcode installation &  system server (if fail OCR)
Progress: 10%
Current status: Need to manual key in using key board if OCR fail to read (but still have potiential for wrong input). Recommend Barcode scanner to install in order to ensure no failure (poka yoke)- 2nd priority
Current status: Under discussion with waftech group.

🎯 Close loop control system & verification
Progress:57%
Current status: Still under verification & improvement.
Due date: 7-June-2016


Overall progress to production mode: 83.5%

➖➖➖➖➖➖➖➖

WAFTECH#3 CU PILLAR UPDATE

🎯UV detaper not effective enough
Progress: 20%
Current status: Hardware designing stage.
Due date: 27 June 2016

➖➖➖➖➖➖➖➖

🎯 Today activity:
-Continue cycle run with dummies (15pcs) to verify machine consistency and performance.
-Increase transfer arm pick and place speed. Found that software need to add in deceleration while transfer arm pick, or place (slow down).
-Few software issue detected today at transfer arm pick and place. Already discuss with Jacky

Thursday 2 June 2016

02-JUN-2016

🕸 Report date: 02-JUN-2016🕸
WAFTECH#3 CU SMT UPDATE

🎯Install label linear remover assembly
Progress: 65%
Current status: Design concept final stage 90%. Pending fabrication.
Due date: 17-June-2016 (improvement plan-can buy off without this first)

🎯 MC not detect if temperature thermal release out of spec
Progress:50%
Current status: Pending software
Due date: TBA
(Temperature controller setup complete, pending software)

🎯 Barcode installation &  system server (if fail OCR)
Progress: 10%
Current status: Need to manual key in using key board if OCR fail to read (but still have potiential for wrong input). Recommend Barcode scanner to install in order to ensure no failure (poka yoke)- 2nd priority
Current status: Under discussion with waftech group.

🎯 Close loop control system & verification
Progress:55%
Current status: Still under verification & improvement.
Due date: 7-June-2016


Overall progress to production mode: 83.5%

➖➖➖➖➖➖➖➖

WAFTECH#3 CU PILLAR UPDATE

🎯UV detaper not effective enough
Progress: 20%
Current status: Hardware designing stage.
Due date: 27 June 2016

➖➖➖➖➖➖➖➖

🎯 Today activity:
-Continue cycle run with dummies (20pcs) to verify machine consistency and performance.
-Encounter mounting waste tape gripper was intermittent to grip waste yape with both gripper. Add in a fabrication part (temporary) to support waste tape, the result is more stable and consistency.
-Few software issue detected today. Mounter tape low alarm, must detect before start a new job, or it will be hard to access into machine to replace a new tape.
-Machine not detect if thermal release out of spec. Temperature controller set up complete, pending for software to update

Wednesday 1 June 2016

01-JUN-2016

🕸 Report date: 01-JUN-2016🕸
WAFTECH#3 CU SMT UPDATE

🎯Install label linear remover assembly
Progress: 65%
Current status: Design concept final stage 80%. Pending fabrication.
Due date: 17-June-2016 (improvement plan-can buy off without this first)

🎯 MC not detect if temperature thermal release out of spec
Progress:0%
Current status: Pending software
Due date: TBA

🎯 Barcode installation &  system server (if fail OCR)
Progress: 10%
Current status: Need to manual key in using key board if OCR fail to read (but still have potiential for wrong input). Recommend Barcode scanner to install in order to ensure no failure (poka yoke)- 2nd priority
Current status: Under discussion with waftech group.

🎯 Close loop control system & verification
Progress:55%
Current status: Still under verification & improvement.
Due date: 7-June-2016


Overall progress to production mode: 83.5%

➖➖➖➖➖➖➖➖

WAFTECH#3 CU PILLAR UPDATE

🎯UV detaper not effective enough
Progress: 20%
Current status: Hardware designing stage.
Due date: 27 June 2016

➖➖➖➖➖➖➖➖

🎯 Today activity:
-Continue cycle run with dummies (40pcs) to verify machine consistency and performance.
-Encounter mounting tape pincher sequence need improvement. To be discuss with software.
-Few software bug detected today, and already highlighted to software engineer for improvement.

note:
Lim/Chan/Jacky, pls expedite to provide "Manual Book" which consist:
1- Mc Part List
2- SOP/WI
3- Engineering Maintenance/PM & Periodic
4- Troubleshooting (error code-remedies-to-fix
5. Consumables Part

Tuesday 31 May 2016

31-MAY-2016

🕸 Report date: 31-MAY-2016🕸
WAFTECH#3 CU SMT UPDATE

🎯Install label linear remover assembly
Progress: 60%
Current status: Design concept final stage. Pending fabrication.
Due date: 17-June-2016 (improvement plan-can buy off without this first)

🎯 MC not detect if temperature thermal release out of spec
Progress:0%
Current status: Pending software
Due date: TBA

🎯 Barcode installation &  system server (if fail OCR)
Progress: 10%
Current status: Need to manual key in using key board if OCR fail to read (but still have potiential for wrong input). Recommend Barcode scanner to install in order to ensure no failure (poka yoke)- 2nd priority
Current status: Under discussion with waftech group.

🎯 Close loop control system & verification
Progress:40%
Current status: Only pick&place, labeling, and robot arm verified. Others will continue check.
Due date: 7-June-2016


Overall progress to production mode: 83.5%

➖➖➖➖➖➖➖➖

WAFTECH#3 CU PILLAR UPDATE

🎯UV detaper not effective enough
Progress: 20%
Current status: Hardware designing stage.
Due date: 27 June 2016

➖➖➖➖➖➖➖➖

🎯 Today activity:
-Chuck table mounter vacuum leak. Change new tube-solved
-Bug checking: Error found at Thermal release- not detect carrier if vacuum out of spec.
-Buy off 3 wafer. OK, no error/reject found.

Note:
Buy off 3 wafer: 10 min 38 sec - No issue
Now pending verified all close loop system with Software Engineer.
Jacky software, pls come tomorrow

Monday 30 May 2016

30-MAY-2016

🕸 Report date: 30-MAY-2016🕸
WAFTECH#3 CU SMT UPDATE

🎯Install label linear remover assembly
Progress: 50%
Current status: Design concept final stage. Pending fabrication.
Due date: 17-June-2016 (improvement plan-can buy off without this first)

🎯 MC not detect if temperature thermal release out of spec
Progress:0%
Current status: Pending software
Due date: TBA

🎯 Barcode installation &  system server (if fail OCR)
Progress: 10%
Current status: Need to manual key in using key board if OCR fail to read (but still have potiential for wrong input). Recommend Barcode scanner to install in order to ensure no failure (poka yoke)- 2nd priority
Current status: Under discussion with waftech group.

Overall progress to production mode: 83%

➖➖➖➖➖➖➖➖

WAFTECH#3 CU PILLAR UPDATE

🎯UV detaper not effective enough
Progress: 20%
Current status: Hardware designing stage.
Due date: 27 June 2016

➖➖➖➖➖➖➖➖

🎯 Today activity:
-Fix known outstanding software bug
-Simulate wafer run to verify software bug.
-Change glass unstack sequence to make machine more stable.

Note:
waftech pls work out on close loop control system as per email asap

Saturday 28 May 2016

28-MAY-2016

🕸 Report date: 28-MAY-2016🕸
WAFTECH#3 CU SMT UPDATE

🎯Install label linear remover assembly
Progress: 50%
Current status: Design concept final stage. Pending fabrication.
Due date: 17-June-2016 (improvement plan-can buy off without this first)

🎯 MC not detect if temperature thermal release out of spec
Progress:0%
Current status: Pending software
Due date: TBA

🎯 Barcode installation &  system server (if fail OCR)
Progress: 10%
Current status: Need to manual key in using key board if OCR fail to read (but still have potiential for wrong input). Recommend Barcode scanner to install in order to ensure no failure (poka yoke)- 2nd priority
Current status: Under discussion with waftech group.

Overall progress to production mode: 83%

➖➖➖➖➖➖➖➖

WAFTECH#3 CU PILLAR UPDATE

🎯UV detaper not effective enough
Progress: 20%
Current status: Hardware designing stage.
Due date: 27 June 2016

➖➖➖➖➖➖➖➖

🎯 Today activity:
-Fix known outstanding software bug
-Simulate wafer run to verify software bug.
-Change glass unstack sequence to make machine more stable.

Note:
waftech pls work out on close loop control system as per email asap.

Friday 27 May 2016

27-MAY-2016

🕸 Report date: 27-MAY-2016🕸
WAFTECH#3 CU SMT UPDATE

🎯Install label linear remover assembly
Progress: 40%
Current status: Design concept final stage. Pending fabrication.
Due date: 17-June-2016 (improvement plan-can buy off without this first)

🎯Software: Pick & Place label "recovery mode" if mc fail to place/pick the label.
Progress: 0%
Current status: Awaiting software engineer next Monday.
Due date: 3-June-2016

🎯 Barcode installation &  system server (if fail OCR)
Progress: 10%
Current status: Need to manual key in using key board if OCR fail to read (but still have potiential for wrong input). Recommend Barcode scanner to install in order to ensure no failure (poka yoke)
Current status: Under discussion with waftech group.

Overall progress to production mode: 80%

➖➖➖➖➖➖➖➖

WAFTECH#3 CU PILLAR UPDATE

🎯UV detaper not effective enough
Progress: 20%
Current status: Hardware designing stage.
Due date: 27 June 2016

➖➖➖➖➖➖➖➖

🎯 Today activity:
-Fix & verify circular cutter performance. Lifted tape solve by change the sequence.
-Further compile additional software bug for software engineer.

Note:
BS Teoh pls discuss with Alex on add-on hand held barcode scanning system