Friday 27 May 2016

27-MAY-2016

🕸 Report date: 27-MAY-2016🕸
WAFTECH#3 CU SMT UPDATE

🎯Install label linear remover assembly
Progress: 40%
Current status: Design concept final stage. Pending fabrication.
Due date: 17-June-2016 (improvement plan-can buy off without this first)

🎯Software: Pick & Place label "recovery mode" if mc fail to place/pick the label.
Progress: 0%
Current status: Awaiting software engineer next Monday.
Due date: 3-June-2016

🎯 Barcode installation &  system server (if fail OCR)
Progress: 10%
Current status: Need to manual key in using key board if OCR fail to read (but still have potiential for wrong input). Recommend Barcode scanner to install in order to ensure no failure (poka yoke)
Current status: Under discussion with waftech group.

Overall progress to production mode: 80%

➖➖➖➖➖➖➖➖

WAFTECH#3 CU PILLAR UPDATE

🎯UV detaper not effective enough
Progress: 20%
Current status: Hardware designing stage.
Due date: 27 June 2016

➖➖➖➖➖➖➖➖

🎯 Today activity:
-Fix & verify circular cutter performance. Lifted tape solve by change the sequence.
-Further compile additional software bug for software engineer.

Note:
BS Teoh pls discuss with Alex on add-on hand held barcode scanning system