Friday 3 June 2016

03-JUN-2016

🕸 Report date: 03-JUN-2016🕸
WAFTECH#3 CU SMT UPDATE

🎯Install label linear remover assembly
Progress: 65%
Current status: Design concept final stage 90%. Pending fabrication.
Due date: 17-June-2016 (improvement plan-can buy off without this first)

🎯 MC not detect if temperature thermal release out of spec
Progress:50%
Current status: Pending software
Due date: TBA
(Temperature controller setup complete, pending software)

🎯 Barcode installation &  system server (if fail OCR)
Progress: 10%
Current status: Need to manual key in using key board if OCR fail to read (but still have potiential for wrong input). Recommend Barcode scanner to install in order to ensure no failure (poka yoke)- 2nd priority
Current status: Under discussion with waftech group.

🎯 Close loop control system & verification
Progress:57%
Current status: Still under verification & improvement.
Due date: 7-June-2016


Overall progress to production mode: 83.5%

➖➖➖➖➖➖➖➖

WAFTECH#3 CU PILLAR UPDATE

🎯UV detaper not effective enough
Progress: 20%
Current status: Hardware designing stage.
Due date: 27 June 2016

➖➖➖➖➖➖➖➖

🎯 Today activity:
-Continue cycle run with dummies (15pcs) to verify machine consistency and performance.
-Increase transfer arm pick and place speed. Found that software need to add in deceleration while transfer arm pick, or place (slow down).
-Few software issue detected today at transfer arm pick and place. Already discuss with Jacky

Thursday 2 June 2016

02-JUN-2016

🕸 Report date: 02-JUN-2016🕸
WAFTECH#3 CU SMT UPDATE

🎯Install label linear remover assembly
Progress: 65%
Current status: Design concept final stage 90%. Pending fabrication.
Due date: 17-June-2016 (improvement plan-can buy off without this first)

🎯 MC not detect if temperature thermal release out of spec
Progress:50%
Current status: Pending software
Due date: TBA
(Temperature controller setup complete, pending software)

🎯 Barcode installation &  system server (if fail OCR)
Progress: 10%
Current status: Need to manual key in using key board if OCR fail to read (but still have potiential for wrong input). Recommend Barcode scanner to install in order to ensure no failure (poka yoke)- 2nd priority
Current status: Under discussion with waftech group.

🎯 Close loop control system & verification
Progress:55%
Current status: Still under verification & improvement.
Due date: 7-June-2016


Overall progress to production mode: 83.5%

➖➖➖➖➖➖➖➖

WAFTECH#3 CU PILLAR UPDATE

🎯UV detaper not effective enough
Progress: 20%
Current status: Hardware designing stage.
Due date: 27 June 2016

➖➖➖➖➖➖➖➖

🎯 Today activity:
-Continue cycle run with dummies (20pcs) to verify machine consistency and performance.
-Encounter mounting waste tape gripper was intermittent to grip waste yape with both gripper. Add in a fabrication part (temporary) to support waste tape, the result is more stable and consistency.
-Few software issue detected today. Mounter tape low alarm, must detect before start a new job, or it will be hard to access into machine to replace a new tape.
-Machine not detect if thermal release out of spec. Temperature controller set up complete, pending for software to update

Wednesday 1 June 2016

01-JUN-2016

🕸 Report date: 01-JUN-2016🕸
WAFTECH#3 CU SMT UPDATE

🎯Install label linear remover assembly
Progress: 65%
Current status: Design concept final stage 80%. Pending fabrication.
Due date: 17-June-2016 (improvement plan-can buy off without this first)

🎯 MC not detect if temperature thermal release out of spec
Progress:0%
Current status: Pending software
Due date: TBA

🎯 Barcode installation &  system server (if fail OCR)
Progress: 10%
Current status: Need to manual key in using key board if OCR fail to read (but still have potiential for wrong input). Recommend Barcode scanner to install in order to ensure no failure (poka yoke)- 2nd priority
Current status: Under discussion with waftech group.

🎯 Close loop control system & verification
Progress:55%
Current status: Still under verification & improvement.
Due date: 7-June-2016


Overall progress to production mode: 83.5%

➖➖➖➖➖➖➖➖

WAFTECH#3 CU PILLAR UPDATE

🎯UV detaper not effective enough
Progress: 20%
Current status: Hardware designing stage.
Due date: 27 June 2016

➖➖➖➖➖➖➖➖

🎯 Today activity:
-Continue cycle run with dummies (40pcs) to verify machine consistency and performance.
-Encounter mounting tape pincher sequence need improvement. To be discuss with software.
-Few software bug detected today, and already highlighted to software engineer for improvement.

note:
Lim/Chan/Jacky, pls expedite to provide "Manual Book" which consist:
1- Mc Part List
2- SOP/WI
3- Engineering Maintenance/PM & Periodic
4- Troubleshooting (error code-remedies-to-fix
5. Consumables Part