🕸 Report date: 01-JUN-2016🕸
WAFTECH#3 CU SMT UPDATE

🎯Install label linear remover assembly
Progress: 65%
Current status: Design concept final stage 80%. Pending fabrication.
Due date: 17-June-2016 (improvement plan-can buy off without this first)

🎯 MC not detect if temperature thermal release out of spec
Progress:0%
Current status: Pending software
Due date: TBA

🎯 Barcode installation &  system server (if fail OCR)
Progress: 10%
Current status: Need to manual key in using key board if OCR fail to read (but still have potiential for wrong input). Recommend Barcode scanner to install in order to ensure no failure (poka yoke)- 2nd priority
Current status: Under discussion with waftech group.

🎯 Close loop control system & verification
Progress:55%
Current status: Still under verification & improvement.
Due date: 7-June-2016


Overall progress to production mode: 83.5%

➖➖➖➖➖➖➖➖

WAFTECH#3 CU PILLAR UPDATE

🎯UV detaper not effective enough
Progress: 20%
Current status: Hardware designing stage.
Due date: 27 June 2016

➖➖➖➖➖➖➖➖

🎯 Today activity:
-Continue cycle run with dummies (40pcs) to verify machine consistency and performance.
-Encounter mounting tape pincher sequence need improvement. To be discuss with software.
-Few software bug detected today, and already highlighted to software engineer for improvement.

note:
Lim/Chan/Jacky, pls expedite to provide "Manual Book" which consist:
1- Mc Part List
2- SOP/WI
3- Engineering Maintenance/PM & Periodic
4- Troubleshooting (error code-remedies-to-fix
5. Consumables Part