Thursday, 15 October 2015

Day 1 after review with Sabran

Inari attendance:
1. Alif (013-4063267)
2. Lokman Trainee (010-5614518)
Waftech attendance:
NA

WAFTECH # 1
Progress:
1. Setup back waftech after long time idle.
2. Replace purple tape with white tape (production).
3. Test run silicon production. Somebody change the program, its run like cu piller step.
4. Bypass taping 1, continue test.
5. Observed roller loose. tape delamination, bubble & cutting offset.
6. Tighten the roller, adjust the speed of roller, same result.

Bubble

Offset cutting

Loose roller



WAFTECH # 3 
Idle. No progress due to no waftech worker.